Alliant Energy and MJ Electric are replacing underground electric lines and converting some overhead electric lines to underground on the southeast side of Cedar Rapids. This will ensure safe and reliable service to the neighborhood.
M.J. Electric completed the installation of conduit and wires.
From October 2022 to December 2022, Alliant Energy crews will convert the overhead lines to underground by connecting cables. During this process, you may experience a brief outage. Alliant Energy will contact you before any scheduled outage.
Following construction, necessary repairs to restore property will be made as efficiently as possible. For questions on property restoration, please call M.J. Electric at (906) 239-0803.
area impacted | anticipated start date |
project type | anticpated construction completion date |
anticipated restoration completion date |
---|---|---|---|---|
Andover Lane SE
|
October 2022 | Connecting underground cables | December 2022 | 2022 |
Ashland Ct SE
|
October 2022 | Connecting underground cables | December 2022 | 2022 |
Ellwin Lane SE | October 2022 | Connecting underground cables | December 2022 | 2022 |
Indiandale Road SE | October 2022 | Converting overhead lines to underground and connecting underground cables | December 2022 | 2022 |
Tahoe Ct SE | October 2022 | Connecting underground cables | December 2022 | 2022 |
Tahoe Lane SE | October 2022 | Connecting underground cables | December 2022 | 2022 |
Thunderbird Road SE | October 2022 | Converting overhead lines to underground and connecting underground cables | December 2022 | 2022 |
Tomahawk Trail SE (North) | October 2022 | Converting overhead lines to underground and connecting underground cables | December 2022 | 2022 |
Tomahawk Trail SE (South) | October 2022 | Converting overhead lines to underground and connecting underground cables | December 2022 | 2022 |
Alliant Energy and M.J. Electric will upgrade overhead electric lines to underground near Red Fox Road SE on the southeast side of Cedar Rapids. This will ensure safe and reliable service to the neighborhood.
M.J. Electric completed the installation of conduit and wire.
From August 2022 to December 2022, Alliant Energy crews will convert the overhead lines to underground by connecting cables. During this process, you may experience a brief outage. Alliant Energy will contact you before any scheduled outage.
Following construction, necessary repairs to restore property will be made as efficiently as possible. For questions on property restoration, please call M.J. Electric at (906) 239-0803.
If you are interested in converting to an underground service drop at your home, please fill out the Construction Contact Form. You are responsible for any costs related to this conversion. An electrician would need to replace your existing meter socket from an overhead meter socket to an underground meter socket.
anticipated start date | project type | anticipated construction completion date | anticipated restoration completion date |
---|---|---|---|
August 2022
|
Connecting underground cables |
December 2022 |
December 2022 |
Alliant Energy is converting overhead electric lines to underground near Harold Drive SE and 36th Street SE on the southeast side of Cedar Rapids. This will ensure safe and reliable service to the neighborhood.
During this process, you may experience a brief outage. Alliant Energy will contact you before any scheduled outage.
Following construction, necessary repairs to restore property will be made as efficiently as possible.
anticipated start date | project type | anticipated construction completion date | anticipated restoration completion date |
---|---|---|---|
February 2022 | Converting overhead lines to underground | August 2022 |
November 2022 |

Alliant Energy is converting overhead electric lines to underground near 30th Street SE on the southeast side of Cedar Rapids. This will ensure safe and reliable service to the neighborhood.
During this process, you may experience a brief outage. Alliant Energy will contact you before any scheduled outage.
Following construction, necessary repairs to restore property will be made as efficiently as possible.
ANTICIPATED START DATE | PROJECT TYPE | ANTICIPATED CONSTRUCTION COMPLETION DATE | ANTICIPATED RESTORATION COMPLETION DATE |
---|---|---|---|
March 2022 | Converting overhead lines to underground | August 2022 |
November 2022 |

Alliant Energy and M.J. Electric are converting overhead electric lines to underground near Memorial Drive SE and 28th Street SE on the southeast side of Cedar Rapids. This will ensure safe and reliable service to the neighborhood.
M.J. Electric will be completing the underground boring, which is expected to be complete in September 2022.
Alliant Energy crews will begin converting overhead lines to underground in October 2022.
Following construction, necessary repairs to restore property will be made as efficiently as possible. For questions on property restoration, please call M.J. Electric at (906) 239-0803.
ANTICIPATED START DATE | PROJECT TYPE | ANTICIPATED CONSTRUCTION COMPLETION DATE | ANTICIPATED RESTORATION COMPLETION DATE |
---|---|---|---|
October 2022 | Converting overhead lines to underground | October 2022 |
November 2022 |
Alliant Energy is converting overhead electric lines to underground on the southeast side of Cedar Rapids. This will ensure safe and reliable service to the neighborhood.
Installation of conduit and wires has been completed.
Alliant Energy crews will convert the overhead lines to underground by connecting cables. During this process, you may experience a brief outage. Alliant Energy will contact you before any scheduled outage.
Following construction, necessary repairs to restore property will be made as efficiently as possible. For questions on property restoration, please call (319) 786-7777.
AREA IMPACTED | ANTICIPATED START DATE | PROJECT TYPE | ANTICIPATED CONSTRUCTION COMPLETION DATE | ANTICIPATED RESTORATION COMPLETION DATE |
---|---|---|---|---|
34th St. SE | May 2022 | Converting overhead lines to underground | November 2022 |
December 2022 |
34th St. SE to Bever Ave SE | July 2022 | Converting overhead lines to underground | November 2022 |
December 2022 |
Bever Ave SE to Parkview Ave SE | July 2022 | Converting overhead lines to underground | November 2022 | December 2022 |