You will see the site, near the intersection of Bunker Hill Road and Finley Street, undergo changes throughout the construction process.
Bunker Hill substation rebuild (Dubuque, Iowa)
We're rebuilding the Bunker Hill substation to expand capacity and help us meet your needs today and into the future.
Proposed project timeline
First half of 2026
- Install a temporary substation near the existing site in the 1800 block of Finley Street.
- Remove existing substation and vegetation with equipment including a crane.
- Install a temporary fence around the entire site.
- Complete the foundation and below-grade work for the new expanded substation.
- Construct a new screening wall that will temporarily close some sidewalks.
Second half of 2026
- Start constructing the new substation inside the new screening wall.
- Receive deliveries at the site and temporarily utilize equipment, including a crane.
- Remove the temporary substation and return the site land to its natural state.
Project photos
Safety
The safety of our customers, employees and contractors is our top priority.
Please avoid closed sidewalks and equipment throughout the project.