Requirements for pole attachment

The following requirements must be met before any wireline or associated equipment attachment is made to an ITC facility.

  1. A copy of a fully executed Third Party Pole Attachment Agreement must be on file (or in process) at Alliant Energy’s corporate office. If you do not have an existing agreement, please email [email protected].
  2. A Pole Attachment Request Application Form [.xlsx] must be emailed to [email protected]. (Note: This form is used for cell phone equipment, cable television or fiber optic communication cables, antennas and communication dishes.)
  3. Completion of a field engineering review of all structures and approval of each attachment.